CIVIL ENGINEER CONSTRUCTION WORKS, PROCUREMENT, INSTALLATION AND COMMISSIONING OF ELECTROMECHANICAL SYSTEMS FOR THE MODERN TRAMWAY AND IMPLEMENTATION STUDIES IN THE WIDER ATHENS REGION
Owner: TRAM S.A.
Budget: 223,920,000 €
Time of construction: 2001 – 2004
Short Description:

Double-line tramway construction, 25 km in length, in the wider Athens region (branch from N. Faliro to Glyfada and branch from P. Faliro to Syntagma).

THEMELI constructed a 6-km long branch between N. Faliro and Glyfada.

  • Civil engineering works
  • construction of tram lane infrastructure
  • construction of major and minor technical works
  • line layer construction
  • construction of stations and terminals
  • landscaping
  • Installation and commissioning of power supply, electricity supply, signalling and rolling stock electromechanical systems.
  • Construction of depots and vehicle maintenance shop at the old Elliniko Airport.